Eight stages of data center commissioning - breakdown

Eight stages of data center commissioning - breakdown

Table of Content

Any data center commissioning project needs to be properly broken down and structured, as that allows the managers to keep track of the progress, and the budget, and minimize any potential risks. 

Most companies will simply adhere to the ASHRAE Guideline 0, which covers five levels: Factory Testing, Delivery and Pre-Installation Testing, Pre-Commissioning and Pre-Functional Start-up, System Functional Performance Testing, and Integrated System Testing.

However, it is our opinion that these five levels are insufficient and are missing a few key elements of the process. That being said, we usually add three more levels to the mix: Design and Planning (as level 1), Handover (as level 7), and Final Report and Document Handover (as level 8).

Don’t worry - adding a few extra levels still keeps you in line with industry standards, including ASHRAE, BCxA, and BSRIA.

What’s more, some companies will further build on these levels, with flow diagrams, and various programs, and will work in a way that prevents them to proceed onto the next level, until the previous one had been completed. 

True, there are companies that do data center commissioning without the use of levels, but it’s a gamble, and with so much at stake, it is our opinion that it’s simply not worth it.

Those that want to take it a step further will also introduce colored tags. By color-coding systems and components, everyone involved in the project gets a quick and easy visual indication of the status of the project, and the current phase of the process. 

Usually, levels 1, 7, and 8 will have no tags, while levels 1-5 will be tagged as red, yellow, green, blue, and white. The tags would carry important information, such as level number, reference, gear ID, project number, date, contractors’, vendors’, designers’, and commissioning agents’ signatures, and a short description of the next step. 

Now, let’s take a closer look at each individual level:

Level 1: Design and Planning

These are all the things that should be completed during the first stage: 

  • Set up the commissioning team
  • Prepare project requirements
  • Draft a Basis of Design (BOD) paper
  • Set up the budget
  • Draft the commissioning program
  • Establish a format for the commissioning reports
  • Establish acceptance criteria
  • Finalize all the necessary commissioning paperwork
  • Wrap up commissioning documentation
  • Work out the training requirements
  • Draft reports
  • Meet with the team
  • Evaluate and review the design and project details
  • Prepare a checklist
  • Identify monitoring software
  • Set up a high-level strategy for the data center commissioning project
  • Set up a high-level training program
  • Come up with the format for the manuals for both the operation and maintenance
  • Meet with the main contractor
  • Do not provide tags just yet

Level 2 – Factory Testing

Factory testing is pretty self explanatory - the gear will be tested, at the factory site, to make sure it works and operates as intended, and as required by the project’s owners/managers. 

During the test, the gear’s performance will be tested in a lab-type environment. Should the gear pass these tests, they get approved by the commissioning manager, and can be signed to be shipped to the site. 

At this point, the gear can be given a red tag, as a simple visual cue that it is currently at level 2. The tags should be signed by both the contractor (or vendor) and the designer, as well as the commissioning agent. 

Level 3 - Delivery and Pre-Installation Testing

When the tested gear makes it to the site, a designated manager should double-check to confirm that the items delivered are the same as those that are ordered, and that meet the requirements of the project. It is pivotal that this step of the project is done *before* the gear is offloaded.

After completing this stage, the designated manager should also check the storage and pre-installation, to make sure the process is in line with the project’s plan. Everything needs to be properly documented.

Usually, project managers would use checksheets to record and keep tabs on the process.

At this point, the gear can be given a yellow tag, as a simple visual cue that this is currently at level 3. The tags should be signed by both the contractor (or vendor) and the designer, as well as the commissioning agent.

Level 4 - Pre-Commissioning and Pre-Functional Start-up

By now, the general contractor and other vendors had installed all the gear, leaving project managers to double-check if the installation had been done in line with the plans and the design, if it has been done according to the guidelines, and in compliance with any local laws and regulations. 

After the completion of this step, it is time for the pre-commissioning/pre-functional and startup testing.

Make sure to properly document and structure the work.

These are the steps to follow:

  • Basic system installation inspection (cables, powerlines, etc.)
  • Gear installation inspection
  • Pre-commissioning/pre-functional inspection of items that will be used in future commissioning assignments 
  • Energize Systems to conclude pre-functional and start-up tasks
  • Manufacture startup analysis
  • Confirm the systems are ready to move to the next stage 

At this point, the gear can be given a green tag, as a simple visual cue that this is currently at level 3. The tags should be signed by both the contractor (or vendor) and the designer, as well as the commissioning agent.

Level 5 – System Functional Performance Testing

Make no mistake - there is plenty of hard work to be done on level 5. That being said, make sure you plan it out very early int he project. Any loose ends coming in from previous levels will be severely multiplied at this stage, so it’s absolutely crucial everything is nice and tight, as you prepare to head into level 5. 

By the time level 5 is completed, you will have brought together, and integrated, various different systems of the data center. This should enable both the team and the commissioning agent, the verification process confirming the task has been completed as per the project’s documentation.

Level 5 should have a detailed, developed strategy, outlined in the commissioning program. That way, all involved parties will know, at any given time, what their tasks are. This is crucial, as this stage involves many different vendors and contractors. 

At this point, the gear can be given a blue tag, as a simple visual cue that this is currently at level 3. The tags should be signed by both the contractor (or vendor) and the designer, as well as the commissioning agent.

Level 6 – Integrated System Testing

Now we’ve reached the final testing step, where the integrated system is put to the test. 

It is what the entire endeavor comes down to, and at this stage, it’s everyone’s responsibility - the designers’, contractors’, vendors’, and everyone else’s, who’s been involved in the building and setting up of the data center. 

What’s more, Level 6 is the pivotal moment - if it fails, the data center doesn’t get signed off, and all the hard work that’s been put into the project will have gone to waste.

The goal of this level is to prove that all systems have been installed as per the documents and requirements, that they are fully operational, and that they work well in unison.

It’s usually split into two parts: Heat Load Test (the testing of the mechanical systems), and the Electrical Integrated Testing (the testing of the electrical systems). These two parts are conducted separately, and have different goals. 

The goal of the Heat Load Test is to prove that the premises keep heat levels within tolerable levels, regardless of the conditions. The goal of the Electrical Integrated Test is to prove that the data center can remain operational even if some electrical systems or utility supplies fail. 

Here are the tasks that need to be done during level 6: 

  • Make sure all parties approve of all testing scripts, and that they are aware of the desired testing outcomes
  • In case you’re testing new installation with current client systems, make sure everyone’s on board
  • Make sure everyone knows the part they’re playing
  • Make sure earlier system functional testing have been successfully completed and signed off
  • Make sure you have the proper instruments and gear to harvest testing data
  • Make sure you have the right amount of temporary load, which can be tweaked as required
  • Make sure everyone agrees on the size of temporary loaders used
  • Make sure everyone agrees on the installation method and temporary loader positioning
  • Confirm loader wiring and power arrangements
  • Make sure everyone agrees on the locations of the testing, the instruments, and the gear
  • Double-check if the gear has the right calibration certification
  • Clean the premises
  • Make sure the test is done in a controlled environment
  • Make sure you can download the data from all sensors
  • Make sure to write, and get approval, of the report, after successfully completing the tests

At this point, the gear can be given a white tag, as a simple visual cue that this is currently at level 3. The tags should be signed by both the contractor (or vendor) and the designer, as well as the commissioning agent.

Level 7 - Handover 

Although not mandatory, it is good to have this level, as a controlled wrap-up of the project. It is usually done through a document that both parties work through, and eventually sign.

This document will list the steps that the clients needs to go through, in order to accept the project, as well as to sign off on the testing information that was provided, which proves the entire system works as intended.

Here are the usual tasks for this level

  • Going through the wrap-up project as outlined in the document
  • Fixing any potential errors 
  • Conducting additional tests, as per the client’s request
  • Having the client accept the fact that the entire system was tested as per the documentation, and was seen as operational

No tags are required at this stage

Level 8 - Final Report and Document Handover

When you make it this far, celebration can already begin. This is the stage at which you’ll be completing any drafted documents, and having them issued for final approval.

By signing, and accepting the documents, the client confirms that the job has been successfully completed.

These documents include:

Testing documents and data for levels 2,3,4 and 5

  • Reports on level 6 work
  • The closeout process on level 7
  • The final report on commissioning
  • Manuals for both operating and maintaining the data center
  • Final sign-off certificate

Related resources

read more stories
Image for Natural Language Processing

Accelerating AI Innovation

Get next-level cloud native capabilities that can help accelerate the development and ...

󰅂
read article
Image for Natural Language Processing

Accelerating AI Innovation

Get next-level cloud native capabilities that can help accelerate the development and ...

󰅂
read article
Image for Natural Language Processing

Accelerating AI Innovation

Get next-level cloud native capabilities that can help accelerate the development and ...

󰅂
read article

The Future of AI Infrastructure: Why More Companies are Opting to Rent Their Own AI Cloud Instances

AI is quickly transforming industries. The global AI software market is expected to reach $126 billion by 2025, thanks to a huge 270% increase in enterprise adoption over the last four years.

󰅂
read article

‍Why AI Digital Cloud Instances Are Superior to Traditional Cloud Services

As the demand for AI-driven applications continues to grow, busit.nesses are seeking cost-effective, high-performance solutions to accelerate their workflows. While traditional cloud services like AWS have long dominated the...

󰅂
read article

AI Regulation and Its Impact on the Tech Industry: What You Need to Know

Artificial intelligence is rapidly becoming one of the most transformative technologies of our time. From autonomous vehicles to predictive analytics, AI is reshaping industries and changing the way we work and live.

󰅂
read article

Ready?

Our team of experts are available and ready to assist you with any inquiries and offer customized 3-5 year financing options that align with your budget and goals.

Contact us